WELCOME to the New In Signal
by author Ivan Ristić...
Promo & Careers | Contact us directly for more info how to advertise for FREE!
ERTMS in Norway – Experiences from half a year of operation
ERTMS in Norway – Experiences from half a year of operation
Bane NOR has embarked on an adventure that involves replacing all existing signalling systems on the Norwegian railway network with ERTMS Level 2 (B3R2).
The ERTMS Programme consists of three sub-projects, comprising a new Traffic Management System, a new ERTMS signalling system, and the retrofitting of approximately 400 railway vehicles with ERTMS.

The new communication-based ERTMS signalling system has been considered a “front runner” in Europe, due to some new initiatives. A centralised architecture made possible due to the EULYNX standardised signalling system interfaces is one of them.
The system is based on ERTMS Baseline 3 (Release 2) and communication between train and track is performed via GSM-R / GPRS. Trains also have a new “invention” on-board since the typical doppler radar is replaced by GNSS.

The aim of the pilot line put into operation back in 2015 was to investigate whether our ideas of a pure ERTMS L2 (B2) infrastructure without optical light signals could be realised. Basic requirements were set up for this line: standardise the signalling infrastructure as much as possible and get the signalling out of the track where possible (ERTMS Level 2 removes optical light signals and axle counters replace track circuits). The pilot has shown that this is entirely feasible also on brownfield infrastructure.

The first line to take the new ERTMS (B3R2) signalling system into operation was a part of the Gjøvik line (its northern part) from Roa station to Gjøvik station. The line is 67 km single track with crossing loops, and an interface (Level transition) to legacy signalling at Roa station. This line is operated by EMUs type Stadler Flirt.

An ERTMS L2 (B2) pilot line has been in operation since 2015. The line is part of the Østfold line, stretching from Ski station, via Mysen station to Sarpsborg. This line is 80 km single track with crossing loops. This line is operated by EMUs type Stadler Flirt.
The pilot line was done as a separate project outside the ERTMS Programme. The pilot line had two initial challenges, one of which was connected to the axle counter system and the other was an implementation issue related to ERTMS onboard, which were both fixed during the first year of operation. The experiences so far with this signalling infrastructure are that it provides a high level of safety, high availability, and limited need for maintenance of the signalling infrastructure.
The “next generation” ERTMS (Level 2 B3R2) was taken into operation in November 2024 on the Gjøvik line. Whilst ERTMS on the pilot line was delivered by Bombardier regarding TMS, Trackside and Onboards, delivery of the first line of the National rollout of ERTMS had a different approach. TMS is delivered by Hitachi, ERTMS Trackside by Siemens and ERTMS in trains by Alstom. ERTMS on the Gjøvik line is built like the Østfold line, but with some adjustments to the engineering.
ERTMS Programme deliveries comprise both the centralised signalling infrastructure and the decentralised infrastructure. Whilst the centralised part of the new signalling infrastructure comprises a computer centre, the decentralised part consists of new trackside objects, such as point machines, axle counters, level crossing systems, etc.

Some of the lessons learned
When moving from legacy signalling to a communication-based digital signalling system, such as ERTMS, there are numerous challenges and numerous learning points. Not only is more accurate data needed, but operationally, the system is also quite different from legacy signalling.
Infrastructure data
Due to the pilot line, we saw that our infrastructure data did not have the required quality needed for ERTMS L2. This resulted in re-measuring the complete railway network to get the required data quality. When moving to such a system, data must be correct, but it is also important to understand how you need to further maintain this data. Understand the supplier’s need for data and transfer of it in a “standardised” format (e.g., RailML) is also required.
Engineering
Engineering of ERTMS must be considered related to the sharing of responsibilities between the Infrastructure Manager (IM) and suppliers (this might differ between IMs). Bane NOR has decided to take the responsibility for information related to infrastructure data for train operations, such as schematic plans, interlocking parameters, speed and gradient profiles. The supplier is responsible for the engineering of the system based on the above input data from Bane NOR.
Our engineering personnel have had to change their mindset from connecting relay contacts to “where should the Marker Board be placed, and why”. We had to make new engineering guidelines to support the engineering of ERTMS.
System supervision
Using both our fibre optic and mobile communication systems to operate ERTMS, therefore ERTMS has to be considered as a system closely integrated with the communication systems. Bane NOR has set up a new National Operation Centre to supervise both ERTMS and communication systems. With ERTMS as a new communication-based system, security is a new issue that must be taken into consideration, also related to system supervision.
Training
With the transfer to ERTMS, a huge amount of personnel need to be trained at different levels, such as train drivers, dispatchers/signallers, signalling engineers, signalling technicians, OAM, security, and Management.
The amount of training needed resulted in Bane NOR building a new training facility to support the training and experience exchange for ERTMS.
Testing
New signalling systems need testing, both related to generic and specific applications. Test of a generic application will typically follow development stages at the start of a project, while test of a specific application will follow the rollout of the signalling systems (or specific changes to it). In addition to the above, which can mainly be performed in a test lab, tests including train runs (dynamic tests) will also be needed.
Bane NOR has established one of Europe’s most advanced test centres in what is named Campus Nyland, a little outside Oslo City Centre. While testing of generic applications will have a somewhat limited duration, the test centre will be heavily used for testing specific application changes.

Half a year of operation
The Gjøvik line was opened to ERTMS operation in November 2024 and has now been operating for more than half a year. This time has provided us with a lot of experience with the new system. NO errors related to either ERTMS or EULYNX interfaces have been discovered. Some minor failures have been found and corrected related to status information in the new Traffic Management System. However, our new development – handheld terminal (HHT) for PICOPS (Person In Charge Of Possessions), has given us some challenges, but now we are starting to get on top of it.
A great statement from the train company operating on this line was:
We don’t like ERTMS, WE LOVE IT 😊